Preferred solution, K12 – Appendix M Mooring system

This report presents the work performed related to the mooring system of the Bjørnafjorden project. The Curved floating bridge with mooring, known as K12, is the recommended solution for the bridge. The curved bridge has 38 pontoons with 125 m centre spacing between each pontoon. Mooring lines will be connected to three pontoons with four lines to each pontoon. This gives a total of 12 mooring lines and anchors for the mooring system.